How often should PG25 be tested? OCP's risk-based schedule explained
MatScienceAI · November 16, 2026 · 10 min read
Short answer
OCP's PG25 Guidelines Rev 2.0 (September 2026) set a floor of one qualified-lab analysis per TCS loop per year, plus a baseline at commissioning. Above that floor the cadence depends on risk. With inline monitoring, compatible materials and an experienced team: annual. No inline monitoring and a team new to the fluid: lab every six months, on-site checks between. Add doubtful materials: quarterly for 18 months, then six-monthly if stable.
OCP's answer is at least once a year at a qualified lab for every technology cooling system (TCS) loop, more often while a loop is new or when the risk is higher. The detail sits in Table 13 of the PG25 Guidelines Rev 2.0, dated 15 September 2026, which sorts loops into low, medium and high risk and gives each a different lab and on-site schedule [1]. One published summary condenses Rev 2.0's sampling guidance to a single row: every loop at least annually, more often for higher-risk loops, with a baseline after start-up [9]. That is accurate, but the row leaves out the part an operator has to plan around: the first 18 months.
We turned Table 13 and its companion chart (Appendix 2) into a month-by-month schedule, counted the samples, and set it beside what six other public documents say.
OCP Rev 2.0 sorts loops by monitoring, materials and familiarity
Risk in Table 13 comes from three conditions, not from rack power or loop size (small loops get separate guidance, covered below) [1]. The three scenarios are:
- Low: inline monitoring is deployed (at least pH and refractive index), the wetted materials are acceptable for the chosen fluid, and the user is familiar with the fluid.
- Medium: no inline monitoring, wetted materials acceptable, user not familiar with the fluid.
- High: no inline monitoring, wetted materials only "mostly acceptable", user not familiar with the fluid.
Material acceptability is judged against Rev 2.0's Tables 3 and 4 (metals, elastomers and plastics) or guidance from the fluid and component suppliers [1]. The table does not cover every combination. A site with inline sensors but a team new to PG25, or an experienced team with no sensors, matches none of the three rows exactly. Rev 2.0 calls the whole table general guidance and says the final frequency depends on use case, expected service events and how often new equipment is added [1]. Our suggestion for a mixed case is to take the higher-risk row until the first 18 months of data are in.
The schedule month by month
The table below reads Table 13 together with the Appendix 2 chart, which plots each tier from month 0 to month 24 [1].
| Risk tier | Lab analysis | On-site testing (pH, refractive index, visual) | After 18 months, if fluid health is stable |
|---|---|---|---|
| Low | Months 0, 12, 24. Optional extra at month 6 in year one | Not required; optional every six months or after an inline sensor anomaly | Stays annual |
| Medium | Months 0, 6, 12, 18 | Months 3, 9, 15, 21 | Lab and on-site may each drop to annual |
| High | Months 0, 3, 6, 9, 12, 15, 18, then 24 | Not required | May drop to lab analysis every six months |
Two things in this table are easy to miss in the text version.
First, bi-annual means every six months. Rev 2.0 uses the word for the medium-risk lab schedule without defining it, and the word is ambiguous in English. The Appendix 2 chart settles it: the medium-risk lab marks fall at months 0, 6, 12 and 18 [1]. The small-loop guidance points the same way, since it says the racks sampled may change every six months [1].
Second, the medium-risk on-site checks fall halfway between lab samples, at months 3, 9, 15 and 21 [1]. So a medium-risk loop gets some chemistry reading every three months during its first 18 months, alternating between a qualified-lab analysis and a quick on-site check. The high-risk loop gets a lab analysis every three months and no on-site requirement at all. Our reading is that the quarterly lab analysis already covers what an on-site check would. Table 13 does not say whether each interim lab sample must cover the full annual minimum panel, so agree the scope with the lab.
Counting the lab analyses in Appendix 2's 24-month window, including the commissioning baseline:
- Low: 3 (months 0, 12, 24), or 4 with the optional six-month sample
- Medium: 4 (months 0, 6, 12, 18), plus 4 on-site checks. If the loop is stable and moves to annual, the next lab sample would fall at month 30 by our arithmetic (18 + 12)
- High: 8 (months 0, 3, 6, 9, 12, 15, 18, 24)
For a site with 12 TCS loops, that is 36 lab samples over two years if every loop qualifies for the low tier, 48 at medium and 96 at high. The jump from low to high is the price of three things at once: no inline pH and refractive index sensors, some doubtful materials, and a team new to the fluid. Rev 2.0 asks for 4 to 6 oz per standard analysis, collected in a clean, unused bottle such as HDPE [1].
The floor: one lab analysis per loop per year, whatever else is installed
Every tier includes an annual qualified-lab analysis. Section 11.2 says each individual TCS loop should be lab-tested at least annually [1], and the inline monitoring section repeats that an annual test is still recommended regardless of monitoring capability, to confirm what the sensors report [1]. Rev 2.0 says the lab should be managed or recommended by the fluid supplier, and that remediation advice should come from the supplier [1]. That matches the PG25 Base Specification, which requires the original fluid manufacturer to offer analytical services through its own or approved third-party labs [2].
The minimum lab panel grew between the 2022 guidelines and Rev 2.0.
| Parameter | 2022 guidelines [3] | Rev 2.0 [1] |
|---|---|---|
| Propylene glycol concentration | Minimum (with freeze point) | Minimum |
| pH | Minimum | Minimum |
| Reserve alkalinity | Minimum | Minimum |
| Visual appearance, sediment | Minimum | Minimum |
| Chloride | Minimum | Minimum |
| Inhibitor concentration(s) | Optional | Minimum |
| Sulfate | Optional | Minimum |
| Total hardness | Optional | Minimum |
| Degradation acids | Optional | Minimum |
| Dissolved metals | Optional | Minimum |
Five items moved from optional to minimum. If a lab contract was written against the 2022 guidelines, it probably buys a smaller panel than Rev 2.0 now expects. The Base Specification's list of what a qualified lab must be able to run names the metals to look for by ICP: copper, iron, lead, tin, zinc, silicon, chromium, molybdenum, nickel and aluminum [2]. It also says test strips are not an acceptable method for glycol concentration, pH or reserve alkalinity in that lab setting [2]. Rev 2.0 allows pH paper on site if no meter is available, while noting it is less reliable [1].
The 2022 guidelines weighted things the other way: on-site testing quarterly, and annual lab analysis only where judged necessary [3]. Rev 2.0 drops the quarterly on-site default and makes the annual lab test the floor for every loop [1].
Event-driven samples sit on top of the calendar
The calendar is the minimum. Several events call for a sample on their own, and different documents list different triggers.
| Trigger | What the source asks for |
|---|---|
| System start-up | Representative sample from each system within the first 1 to 3 days, kept for the life of the fluid and submitted for baseline values; also keep a fresh, unexposed sample [1] |
| Each bulk delivery or lot | Retain an as-received sample for at least six months; it need not be analyzed [1] |
| On-site test out of limits | Send a sample to a qualified lab within one week [1] |
| Inline sensor anomaly not disproven on site | Lab test (low-risk tier) [1] |
| Many service events, or new equipment added | Sample more often for a short interval until the fluid is confirmed stable; Rev 2.0 says this is not a requirement [1] |
| Extreme thermal, pressure or seismic event | External lab analysis recommended [4] |
| Initial fill, significant makeup fluid addition | Lab verification, per ASHRAE TC 9.9's bulletin TCS Coolant Integrity and System Readiness Best Practices (issued in May, per the report), as reported [5] |
| Vacuum fill | Sample and lab test, because glycol mixtures can partly separate under vacuum (same bulletin, as reported) [5] |
| Top-up, mixing or component replacement | Re-test two weeks later [7] |
We could not open the ASHRAE bulletin itself, so the two ASHRAE rows rest on StorageReview's report of it [5], which reports only "a periodic schedule", with no interval. A related rule covers new equipment: if it arrives holding another fluid, such as water or a different PG25 formulation, Rev 2.0 says to flush and fill it with the operating fluid before it joins the loop [1]. Our article on mixing PG25 coolants covers changing products in a running loop.
Other published cadences disagree on what drives risk
Two of the four non-OCP sources give quarterly chemistry for every loop, one scales from quarterly to annual by rack density, and one gives no interval.
| Source | Lab analysis | On-site or routine checks | Basis for the cadence |
|---|---|---|---|
| OCP Rev 2.0, Sep 2026 [1] | Annual to quarterly by risk tier; at least annual | Six-monthly (medium tier) or not required | Inline monitoring, materials, operator familiarity |
| OCP 2022 guidelines [3] | Annual, "if deemed necessary" | Quarterly | Not stated |
| OCP Modular TCS Rev 1, Aug 2025 [4] | Annual external lab, plus after extreme events | Continuous on-site monitoring | Not stated |
| ASHRAE TC 9.9 bulletin, as reported [5] | Initial fill, after makeup or vacuum fill, then periodic | Not reported | Event-driven |
| Tetra Tech green paper, May 2025 [6] | Quarterly complete chemical analysis (pH, contaminants, oxidation); lab or on site not stated | Routine visual inspection of components | Not stated; defers to manufacturer at initial fill |
| Flumetra, Aug 2026 [7] | Commissioning baseline; quarterly chemistry panel; annual programme review | Monthly visual and pressure checks | Tighter in first six months and after fluid additions |
| Alliance Chemical, Apr 2026 [8] | Above 85 kW/rack quarterly; 40-85 kW semi-annual full panel; below 40 kW annual | Reserve alkalinity quarterly to semi-annual by density; titration between lab samples | Rack power density and inhibitor depletion rate |
The real disagreement is about what drives risk. OCP's table keys on whether you can see the fluid between samples (inline sensors), whether the loop's materials suit it, and whether the team knows the fluid [1]. Alliance Chemical keys on rack density, arguing that inhibitor depletion speeds up with temperature, and its chief commercial officer calls quarterly reserve alkalinity testing the minimum defensible position above 85 kW per rack [8]. Neither publishes the data behind its tiers, so a reader cannot check either one. Alliance's schedule also leans on reserve alkalinity, while Rev 2.0's in-use table only asks for reserve alkalinity to be reported for OAT fluids and sets a minimum (above 4 mL by ASTM D1121, on a 10 mL sample) for conventional inhibitor technology [1]. For an OAT fluid, ask the supplier which parameter tracks inhibitor health before you pay for quarterly reserve alkalinity.
The quarterly figures from Tetra Tech and Flumetra are stated without a basis [6][7]. Flumetra cites OCP, ASHRAE TC 9.9 and equipment makers in general terms but gives no document titles or editions [7].
Small loops: OCP accepts sampling a share of racks
For loops under 100 gallons (about 380 L), Rev 2.0 accepts that sampling every rack on schedule may not be practical [1]. It still asks for refractive index (glycol concentration) and pH on every rack before or during start-up, which the rack maker may do. After start-up it suggests a statistically significant subset of racks, analyzed at a qualified lab bi-annually (every six months) at a minimum, noting that the racks chosen may change every six months so that all of them are eventually sampled. If results land in a warning zone, the share goes up, for example from 20% to 40%, to see whether the problem is widespread. The note limits this to racks of similar type with the same materials [1].
As arithmetic, with two assumptions of ours: that 20% (Rev 2.0's example starting rate) is the base share, and that the first round falls at month 6. Then 50 similar racks at 20% is 10 racks a round. Rotating without repeats, the fifth round covers the last 10, so every rack has had one lab sample about two and a half years after start-up (rounds at months 6, 12, 18, 24 and 30). At 40%, 20 racks a round, full coverage comes in the third round, at month 18. Whether 20% counts as a statistically significant subset depends on how alike the racks really are, and Rev 2.0 does not give a method for deciding that.
How we would set a schedule
Classify each loop against Table 13 before commissioning, and pick the higher row when a loop falls between them. Write the resulting calendar, the Rev 2.0 minimum lab panel and the event triggers above into the fluid supply agreement, since the Base Specification already obliges the original fluid manufacturer to offer lab support [2]. Our comparison of the Base Specification and Rev 2.0 covers which in-use limits to put in that agreement.
Then treat month 18 as a review point, not an automatic step-down. Both the medium and high tiers allow a reduction there only if fluid health is stable [1], and that judgement needs trended results under consistent sample and loop names, which Rev 2.0 asks for so that each result can be read against the earlier ones [1]. Inline sensors buy the lowest lab frequency, but they need their own upkeep: Rev 2.0 puts typical sensor life at 1 to 5 years and suggests comparing sensor readings with lab results at a set interval, giving annually or bi-annually as examples [1].
Frequently asked questions
What does bi-annual mean in OCP's PG25 sampling table?
Every six months. Rev 2.0 does not define the word in its text, but its Appendix 2 chart puts the medium-risk lab analyses at months 0, 6, 12 and 18, and the high-risk schedule steps from quarterly to a next sample at month 24. Its guidance for small loops also says the racks sampled may change every six months.
Can on-site pH and refractometer checks replace lab analysis of PG25?
Not under OCP Rev 2.0. It says each TCS loop should be tested at least annually by a qualified lab, and its inline monitoring section repeats that an annual test is still recommended whatever monitoring is installed. On-site checks fill the gaps between lab samples and confirm inline sensor readings.
When should a new PG25 loop first be sampled?
Rev 2.0 asks for a representative sample from each system within the first 1 to 3 days of operation, kept for the life of the fluid and sent for analysis to give baseline values. It also suggests keeping a sample of the fresh fluid that has never touched the system. Table 13 then counts that commissioning analysis as the first point of every risk schedule.
Does rack power density change how often PG25 should be tested?
OCP's Table 13 does not use rack density as a risk factor; it uses inline monitoring, material compatibility and how familiar the operator is with the fluid. Alliance Chemical publishes a density-based schedule with quarterly testing above 85 kW per rack. That is one supplier's position, so agree the cadence with your own fluid supplier.
References
- Guidelines for Using Propylene Glycol-Based Heat Transfer Fluids in Liquid Cooled Racks, Revision 2.0, Version 1.0.0. Open Compute Project, 2026-09-15. https://www.opencompute.org/wp-content/uploads/2026/10/OCP-PG25-Guidelines-V1.0.0.pdf
- Base Specification for Single-Phase Propylene Glycol-Based Cold Plate Coolants (PG 25), Version 1.0.0. Open Compute Project, 2026-07-14. https://www.opencompute.org/documents/ocp-base-specification-pg25-v1-0-0-final-pdf/
- Guidelines for Using Propylene Glycol-Based Heat Transfer Fluids in Single-Phase Cold Plate-Based Liquid Cooled Racks (2022 version). Open Compute Project, 2022. https://www.opencompute.org/documents/guidelines-for-using-propylene-glycol-based-heat-transfer-fluids-in-single-phase-cold-plate-based-liquid-cooled-racks-final-pdf/
- Modular Technology Cooling System for Cloud Scale: Design and Delivery of Liquid to Rack Distribution Systems, Rev 1. Open Compute Project, 2025-08-25. https://www.opencompute.org/documents/ocp-modular-tcs-rev-1-final-2025-pdf
- ASHRAE TC 9.9 flags four ways direct-to-chip cooling loops go wrong. StorageReview, 2026-08-30. https://www.storagereview.com/news/ashrae-tc-9-9-flags-four-ways-direct-to-chip-cooling-loops-go-wrong
- Practical Design Guide to Optimizing Data Center Direct-to-Chip Liquid Cooling with PG 25, Revision 1.1. Tetra Tech (Sam Khalilieh), 2025-05-15. https://www.tetratech.com/wp-content/uploads/2025/05/TTHPBG-PG25-Data-Centre-White-Paper_1.1.pdf
- Coolant testing frequency. Flumetra (Fred Bahari), updated 2026-08. https://flumetra.com/insights/coolant-testing-frequency
- Reserve alkalinity testing cadence (ASTM D1121) for data center coolant. Alliance Chemical (Andre Taki), 2026-04-27. https://alliancechemical.com/blogs/articles/reserve-alkalinity-testing-cadence-astm-d1121
- PG25 Coolant: Property Table, OCP Limits and CDU Derates. K&K Data Service, undated, accessed 2026-11-16. https://www.kkdatasvc.com/lab/pg25-coolant-properties/